http://gruas.usabiaga.com/wp-content/plugins/sociofluid/images/delicious_32.png http://gruas.usabiaga.com/wp-content/plugins/sociofluid/images/technorati_32.png http://gruas.usabiaga.com/wp-content/plugins/sociofluid/images/google_32.png http://gruas.usabiaga.com/wp-content/plugins/sociofluid/images/myspace_32.png http://gruas.usabiaga.com/wp-content/plugins/sociofluid/images/facebook_32.png http://gruas.usabiaga.com/wp-content/plugins/sociofluid/images/yahoobuzz_32.png http://gruas.usabiaga.com/wp-content/plugins/sociofluid/images/twitter_32.png http://gruas.usabiaga.com/wp-content/plugins/sociofluid/images/meneame_32.png

Crane Liebherr LR 11350 for the placement of the dome of Buesa Arena

The redevelopment of the Fernando Buesa Arena Pavilion will a shift in the coming days with the removal of the dome to its new location. This is a spectacular move and a great technical complexity, made of a giant crane being transported to Vitoria in parts through several heavy vehicles.

The crane started to arrive and the Buesa Arena, and due to its size, is mounted in situ in the coming days. This is a structure with potential for up to 1,600 tons-dome canopy weighs just over 200 tons, consists of an arm 120 meters long and working at a height of 70 meters.

Cranes involved:

  • Crane used to assemble the dome: Crane Liebherr LR 11350
  • Cranes used for the preparation of the crane Liebherr LR 11350
    • AC70 DEMAQ city
    • LTM 1060
    • LTM 1150

The transfer of the dome to its new location is a more delicate of all reform. Therefore, Buesa Arena UTE is coordinating the security device to the service of Civil Protection of Vitoria-Gasteiz and Emergency Management of the Basque Government.

This plan covers not only the conditions for the operation itself but also all necessary measures to prevent risks to both the people who will serve on the work as the facilities and the public expected to see the operation go.

Moreover, the Basque Metorología, Euskalmet will facilitate the July 15 joint venture to weather forecasts for the following days. Such information is essential to determine the date of the maneuver, scheduled for those days and can not be done in bad weather.

The renovation and expansion of the Fernando Buesa Arena, which began last March 21, will continue for 15 months and submit to the flag to a major refurbishment to increase capacity up to 15,290 people.

Source: Mail