Liebherr LR 1750 on the withdrawal of the fishing boat 'Motxo'

Liebherr LR 1750 on the withdrawal of the fishing boat 'Motxo'

Crane Liebherr LR 1750. Lifting time 40 minutes. Weighed 184 tons ship. On the spot, the engineer of the operation, Kepa Kruzeta and Patxi Usabiaga oversaw each of the movements. The ship was from the subject yesterday by four nylon slings.

Crane Liebherr LTM 1350 in Henderson Station

Crane Liebherr LTM 1350 in Henderson Station

The roof of the station Herrera was executed in a day less than the 4 provided. The key has been in a perfect planning and synchronization of material and human resources. The star has been a large crane Liebherr LTM 1350 Usabiaga company in which only mark the counterweights 220. tons on the scale.

Usabiaga cranes in the fifth bridge in San Sebastian

Usabiaga cranes in the fifth bridge in San Sebastian

The fifth bridge of San Sebastian takes shape with the placement of your structure. A complex engineering operation at daybreak put the frame construction.

Cranes Usabiaga in placing 5 th Bridge of San Sebastian

Cranes Usabiaga in placing 5 th Bridge of San Sebastian

Parts of 32 meters long and 70 tons. Special transport Usabiaga, at dawn. From Langreo (Asturias), waiting all morning in the special transport trailer-axle multi-up by placing two large cranes.

Liebherr LR 1600/2 mounting beams 200 tons, Ferrovial.

Liebherr LR 1600/2 mounting beams 200 tons, Ferrovial.

Liebherr LR 1600 crane 600 ton crawler, 2009, ideal for assembly of wind farms.
Has the characteristic contrast to a wheel which can move with suspended load.
The crawler crane LR 1600/2 600-ton capacity impresses with basic load for the system variable [...]

Cranes Usabiaga in Orio

Cranes Usabiaga in Orio

Usabiaga cranes involved in the unfolding of Eusko Train routes passing through Orio, affecting 1,635 meters of track. Includes a 580-meter viaduct, in order to resolve the suppression of the level crossing and avoid a wetland.

Mollet work: special transport TITAN CC2000 crane mounting

Mollet work: special transport TITAN CC2000 crane mounting

The works identified in this project, together with the installation of the proposed third lane on the ramp Papiol-Mollet, will allow traffic on this branch of freight and passenger trains both conventional lines as the AVE, guaranteeing access to this branch to new circulations of goods AVE Barcelona-French border and preventing its passage through urban tunnels of Barcelona.

Usabiaga Cranes Bridge in San Juan

Usabiaga Cranes Bridge in San Juan

A gentle maneuver and given relatively simple, repeated seven times, serving to realize the frame of the bridge of San Juan. A pedestrian and vehicle link, Estate of Peace cemetery costs, that now represents a tangible reality. The preparations, starting with a smooth surface [...]

LTM1200 LTM1500 and the Guggenheim Bilbao

LTM1200 LTM1500 and the Guggenheim Bilbao

Jobs at the Guggenheim Museum in Bilbao. Crane 200 Ton and 500 Ton crane jib. Jobs at 51 m radius, weight up to 21 tons in the working radius

Metal frame of 230 Tons in the A-8, Trapagaran. Liebherr LTM 1500 and LTM 1350

Metal frame of 230 Tons in the A-8, Trapagaran. Liebherr LTM 1500 and LTM 1350

Installation of 230-ton steel structure on the A-8 Trapagaran with LTM LTM 1500 and 1350.
In addition to mounting cranes provided transport Usabiaga special.